The short answer
Job profit is total revenue minus total cost for that job — including approved change orders on both sides. Express it as a margin (profit ÷ revenue) to compare jobs of different sizes, and as a markup (profit ÷ cost) only when you need to know what was added on top of cost. Revenue is not profit, and a deposit is not profit either.
Definitions
- Contract price
- What the customer agreed to pay for the original scope.
- Change-order revenue and cost
- Approved additional scope. Both sides must be counted; adding the revenue and forgetting the cost is one of the most reliable ways to overstate profit.
- Job cost
- Every cost the job caused, at the loaded rate — the subject of true job cost.
- Profit margin
- Profit ÷ revenue. The share of the customer's money you kept.
The formulas
Revenue = contract price + approved change-order revenue
Cost = job cost + change-order cost
Profit = revenue − cost
Profit margin = profit ÷ revenue
Markup on cost = profit ÷ cost
Worked example
A $24000 contract that cost $17500 to deliver, plus a change order adding $2200 of revenue and $1600 of cost:
- Revenue: $26,200.00
- Cost: $19,100.00
- Profit: $7,100.00
- Profit margin: 27.10%
- Markup on cost: 37.17%
The change order was priced at a thinner margin than the base contract, so it pulled the whole job's margin down even though it added profit in dollars. Both facts are true at once, and only one of them is visible if you look at dollars alone.
When markup has no answer
If cost is zero, markup is undefined — you cannot express profit as a percentage of nothing. RHACOVA reports that as unknown rather than printing 0% or infinity, because a fabricated number in a profit report is worse than an admitted gap. The same discipline applies to margin when revenue is zero.
Profit is only final when the job is
A job's profit changes until the last invoice, the last subcontractor bill and the last warranty visit. Mid-job, what you have is a projection: committed costs plus forecast plus actuals to date. Treating a mid-job number as final is how a profitable job becomes a surprise. Comparing the final result back to the estimate is the subject of estimate vs actual.
Common mistakes
- Counting change-order revenue and forgetting change-order cost.
- Treating the deposit, or the bank balance, as profit.
- Comparing jobs by profit dollars instead of margin.
- Closing out a job before the final subcontractor invoices arrive.
- Excluding the owner's site hours, which makes small jobs look far better than they are.
Quick answers
- Do change orders count in job profit?
- Yes, on both sides. Approved change-order revenue increases revenue and its cost increases cost. Counting only the revenue overstates the profit.
- Can profit be negative?
- Yes. If costs exceed revenue the job lost money, and reporting it as a small profit only delays the correction.
Run the numbers
Revenue including approved change orders, total cost, profit in dollars, profit margin and markup on cost.
Open the Job Profit CalculatorFree, no account, and the answer stays on the page.
Let the job keep score for you
A RHACOVA Job carries a frozen baseline, actual and committed costs, approved change orders and a projected profit that updates as costs land.
Open JobsHow RHACOVA defines these terms
Every calculator, estimate and job in RHACOVA uses one set of financial definitions, and they are written down rather than implied. Read the RHACOVA methodology for the full list of definitions this article relies on.
Keep reading
- Markup vs Margin for Contractors
Understand and convert between markup and margin when pricing a job.
- How to Price Change Orders Without Losing Profit
Price a construction change order so it does not reduce the job's profit.
- Estimate vs Actual: How Contractors Find Profit Leaks
Compare estimated versus actual job cost and interpret the variance.